AS2566.2 Table 5.6 Explained: GRP Allowable Deflection

The allowable deflection for a GRP buried pipe is governed by AS/NZS 2566.2 — Part 2, Installation — not by the Part 1 design standard. Here's what that limit is for, where it applies, and why it is a different number from the deflection you calculate at design.

Last reviewed July 2026 · AS/NZS 2566.2:2002

If you have searched for "AS2566.2 Table 5.6 GRP deflection", you are almost certainly looking for the allowable deflection of a GRP (glass-reinforced plastic) buried pipe — the limit an installed pipe is checked against. The single most useful thing to know up front is which part of the standard that limit lives in: it is Part 2 (Installation), not Part 1 (Design). Getting that straight is the difference between a clean acceptance test and an argument in the trench.

What Table 5.6 is

AS/NZS 2566.2 is the installation half of the buried flexible pipe standard. Where Part 1 tells you how to calculate a pipe's structural performance, Part 2 governs how the pipe is put in the ground and how the finished installation is verified. Its deflection provisions — including Table 5.6 — set the allowable deflection of the installed pipe: the field acceptance limit.

Because a flexible pipe carries load by mobilising the soil around it, its final deflection is largely a product of how well it was bedded and compacted. The installation acceptance limit exists to confirm that the soil support the design relied on was actually delivered on site.

Read the value from the standard

The specific allowable percentage for your pipe and installation conditions is given in AS/NZS 2566.2:2002 Table 5.6. Read it directly from the current standard rather than a third-party figure — the value can depend on the pipe and the conditions defined there. This article explains what the limit is for and how it is used; it does not reproduce the table.

Where it applies

Table 5.6 comes into play at the installation acceptance stage — after the pipe is bedded, embedded and backfilled, when deflection is measured (typically by a mandrel/proof gauge or a survey) and compared against the allowable limit. In practice that means:

Design vs installed

Design deflection (calculated to AS2566.1) is what you predict from loads and soil support before construction. Allowable installed deflection (AS2566.2 Table 5.6) is the on-site acceptance limit you measure against after backfill. They are related, but they are not the same number and they come from different parts of the standard.

How it differs from the Part 1 design check

In our deflection worked example, the modified Iowa formula predicts a design deflection from load and soil modulus. Table 5.6 sits at the other end of the process — the installed limit you verify against:

Two different deflection numbers
 Design deflectionAllowable installed deflection
StandardAS/NZS 2566.1 (Part 1)AS/NZS 2566.2 Table 5.6 (Part 2)
How obtainedCalculated (modified Iowa)Measured on site
PurposePredict performance at designAccept or reject the installation
WhenBefore constructionAfter backfill
The design deflection is a prediction. The Table 5.6 limit is the promise you check it against.

How the acceptance check works

The installed deflection check is simple in principle:

  1. Install the pipe to the Part 2 requirements — bedding, embedment and compaction as specified.
  2. Measure the vertical diameter reduction after backfill, as a percentage of the pipe diameter.
  3. Compare the measured value against the Table 5.6 allowable for the pipe and conditions.
  4. Accept or investigate — a measured deflection within the limit passes; one that exceeds it triggers investigation and remediation before acceptance.

If the installed deflection is comfortably inside the limit, it confirms the soil support assumed in the Part 1 design was achieved. If it is close to or over the limit, the embedment or compaction likely fell short of what the design assumed.

Common mistakes

Summary

References
Standards Australia (2002). AS/NZS 2566.2:2002 Buried Flexible Pipelines Part 2: Installation. Standards Australia, Sydney.
Standards Australia (1998). AS/NZS 2566.1:1998 Buried Flexible Pipelines Part 1: Structural Design (incorporating Amd 1:2017). Standards Australia, Sydney.

See an error in this article? Contact us — we review every correction against the standard.