Reference 9 min read

AS2566.1 vs AS2566.2: What's the Difference?

One is about how you design a buried flexible pipe. The other is about how you install it. Confusing the two is one of the most common sources of error in Australian and New Zealand pipeline work — here's the plain-English distinction, and which part applies to your task.

Last reviewed July 2026 · AS/NZS 2566.1:1998 (Amd 1:2017) & AS/NZS 2566.2:2002

The two-part standard at a glance

AS/NZS 2566 is the joint Australian/New Zealand standard for buried flexible pipelines — pipes that carry load by deforming and mobilising the surrounding soil, rather than by being rigid enough to resist it alone. That covers PVC, PE (HDPE), GRP, and similar thermoplastic and composite pipes. It is published in two parts, and they answer two different questions:

AS/NZS 2566 — Part 1 vs Part 2
 AS/NZS 2566.1AS/NZS 2566.2
SubtitlePart 1: Structural DesignPart 2: Installation
AnswersWill the pipe perform?How do we put it in the ground?
Used byDesigners / structural & civil engineersContractors, site engineers, inspectors
Key contentLoads, deflection (modified Iowa), buckling, strain, soil modulus E′Trenching, bedding & embedment, compaction, field deflection limits & testing
Life-cycle stageDesign & documentationConstruction & commissioning
The one-line version

You design to Part 1. You build and inspect to Part 2. A calculation that passes Part 1 is only valid if Part 2 is followed on site — because the design assumed a particular quality of embedment and compaction that only the installation can deliver.

Part 1 — Structural design (the calculation)

AS/NZS 2566.1 is where the numbers happen. It takes the loads acting on a buried pipe and checks the pipe against three limit states. If you have used our AS2566 calculator, everything it computes lives in Part 1:

The single most influential input in all of this is the effective soil modulus, E′ — the stiffness of the soil around the pipe. It matters more than the pipe's own stiffness for most installations, which is exactly why installation quality (Part 2) is so decisive. We cover the subtleties of E′ in The E′ Soil Modulus Problem in AS2566.

Note

Part 1 is the 1998 edition, incorporating Amendment No. 1 (2017). When people write "AS2566" with no suffix, they almost always mean Part 1 — it is the part engineers reference day to day.

Part 2 — Installation (the construction)

AS/NZS 2566.2 governs what happens in the trench. A flexible pipe relies on the soil beside it to carry load, so how the pipe is bedded and how well the embedment is compacted is not a construction detail — it is a structural input. Part 2 sets out:

A Part 1 design is a promise about the soil. Part 2 is how you keep it.

This is where the well-known GRP deflection tables live — for example, the allowable deflection limits many engineers search for as "AS2566.2 Table 5.6". Those installation limits belong to Part 2, not Part 1, which is a frequent point of confusion. (A dedicated article on the Part 2 GRP deflection limits is in preparation.)

Which part applies to your task?

A quick way to place any AS2566 question:

Common mistake

Reading a Part 2 installation deflection limit as if it were a Part 1 design output — or vice versa. Design deflection (Part 1) is the value you calculate; allowable field deflection (Part 2) is the acceptance limit you test against on site. They are related but not the same number, and they come from different parts of the standard.

How they work together on a real project

On a typical buried pipe job the two parts are used in sequence, then close the loop:

  1. Design (Part 1). Calculate loads and check deflection, buckling and strain — assuming an embedment material and compaction level, giving an assumed E′.
  2. Specify (Part 1 → Part 2). Translate that assumption into a construction specification: the bedding class and compaction Part 2 requires to actually achieve the E′ you designed with.
  3. Install (Part 2). The contractor builds the trench, beds and embeds the pipe, and compacts to the specified density.
  4. Verify (Part 2). Field deflection is measured after backfill and checked against the allowable installed limit. If it passes, the Part 1 design assumptions have been realised.

Skip or under-deliver on step 3, and the elegant Part 1 calculation is worthless — the pipe simply won't have the soil support the numbers assumed.

Summary

References
Standards Australia (1998). AS/NZS 2566.1:1998 Buried Flexible Pipelines Part 1: Structural Design (incorporating Amendment No. 1:2017). Standards Australia, Sydney.
Standards Australia (2002). AS/NZS 2566.2:2002 Buried Flexible Pipelines Part 2: Installation. Standards Australia, Sydney.

See an error in this article? Contact us — we review every correction against the standard.